Spire is finishing up on the first phase of a new gas main installation along Nashua within the next few weeks. They will then begin work on phase 2, which will start at Ridge Avenue and head south to Craig Street on Nashua with connection tie ins and miscellaneous valves along the way. They hope to begin phase 2 around April 30 and that work will last approximately two months depending on the variables encountered (eg. rock, weather and needed restoration). Please be on the lookout for traffic controls as this gets underway.