Public Works Projects

Posted on: July 25, 2014

[ARCHIVED] 2014 Street Maintenance Pavement Restoration Update 7-25-2014

Concrete work continues and milling to start next week as part of the 2014 Street Maintenance Pavement Restoration project. Concrete crews finished in the Holt Estates subdivision, Fulkerson Court, Bonaire, and Westboro subdivision this week repairing curbs and upgrading sidewalk ramps to ADA compliance. Next week they will move on to Wilshire Blvd. Milling operations will start next week in the Holt Estates subdivision and on Birmingham Road.

Click HERE to see a street map.