- Home
- Your Government
- City Hall Atrium Renovation
City Hall Atrium Renovation
Pardon Our Dust!
Built in 1982, the glass domed atrium at Liberty City Hall has presented a variety of challenges, including temperature control (particularly on the third floor) and many leaky spots. Beginning this spring, the domed roof will be replaced with a structural supported flat roof with vertical glass (pictured above).
In addition to solving the temperature control and water leak issues, this project will include:
- ADA-compliant entryway from Kansas Street with an overhang. New concrete entryway will also mitigate pooling water
- Replaced steps from Kansas Street
- LED decorative lighting along the new roof line
- New flooring on the second floor
Project updates will be provided below as more information is available.
Week of May 22, 2023
A large crane arrived this week and is set up on Kansas Street to do some heavy lifting. The silhouette of City Hall is changing again as crews have begun to install the steel framing. The contractor plans to move the crane to Kansas Street next week for a few days. Due to the width of the crane when the outriggers or retractable stabilizers are in use, Kansas Street parking will be reduced slightly between 6 a.m. - 3 p.m. for Tuesday and Wednesday (weather permitting). Traffic will still be able to get through, but alternate routes are encouraged. The outriggers will be pulled in and the crane will be left inside the construction fencing when it is not in use. Crews have also continued work on the Kansas Street side with more concrete to be poured next week.
Week of May 9, 2023
The silhouette of City Hall has changed this week as crews have begun removing the windows above the atrium and setting forms for the new Kansas Street entryway.
Week of May 1, 2023
Crews began pouring concrete footers in preparation for the Kansas Street entry. In the next week or so, a small crane will be brought in temporarily to help with removal of the atrium windows facing Missouri and Kansas. The crew will then complete waterproofing the ends of the upper atrium. All of this is, of course, weather dependent.
Week of April April 17, 2023
- The scaffolding is up and the plywood floor and wall have been installed on the third floor.
- Demolition of the area in front of the 2nd floor entrance is moving right along.
- The Missouri entrance is now protected by covered scaffolding. Please remember this is where you need to enter City Hall to access any of the floors.
April 13, 2023
The City Hall atrium looks a little different with scaffolding that rises two floors.
April 2023
Construction is slated to begin April 11. Staff and the contractor will strive to maintain access to services at City Hall throughout the project, but because this will be an active construction site, we encourage residents and customers to utilize online services whenever possible in the coming months. Here are two handy webpages to bookmark:
The project will be undertaken in phases. Please note the following closures and changes that will be in place as a part of the construction:
- The Kansas Street entrance to City Hall will be closed for the duration of the project. Visitors will need to use the Missouri Street entrance and access the upper floors via the elevator.
- Street parking along the south side of Kansas Street will be reduced. Street parking along the north side of Kansas Street will remain open and the street will be open to traffic.
- Street parking along Missouri Street will be reduced. The street will remain open to traffic.
- The public parking lots at Missouri and Kansas Streets will remain open during construction.
June 2022
The Liberty City Council approved a contract with JE Dunn for design and construction services to repair the City Hall atrium. City staff worked with the contractor over the next several months to finalize the design and construction plans.
For More Project Updates
To stay up to date on construction progress and any temporary changes in service delivery, sign up for the Liberty News Flash (weekly e-newsletter) »
and follow the City on Facebook »