Progress


  • April 7, 2017: On Friday, April 7 the Liberty City Council and guests celebrated the opening of the City’s new $78.3 million Utilities Operation Center and wastewater treatment facility.
    The Liberty Utilities Operations Center includes the wastewater treatment facility, administration offices, a testing laboratory and maintenance facility. This is the largest single investment to the City’s infrastructure to date.  Grand Opening Photos»
  • Fall 2016: The construction for the Wastewater Treatment facility and infrastructure improvements is nearing a point to allow for the facility to be tested and tuned to take sanitary flow.  The contractor is installing equipment and completing finishes to the buildings and facilities
Waste Water Treatment Plant_Liberty Camera_09282016 sm.jpg

  • July 25, 2016: City Council approved a contract amendment with Goodwin Bro. Construction to include additional scope, including the construction of a new West Trunk Sewer main.
  • August 19, 2015: Official groundbreaking for the Liberty Utilities Operations Center.
    • Located on 26 acres west of Birmingham Road near the southern City limits, the Liberty Utilities Operations Center will include the wastewater treatment facility, administration offices, a testing laboratory and maintenance facility. This is the largest single investment to the City’s infrastructure to date.
    • The City has worked to maximize Liberty’s investment in this new facility. Using a design-build process, the City selected Goodwin Brothers as the contractor for the project with a not-to-exceed fixed cost. City staff also worked with the Missouri Department of Natural Resources to secure a low-interest State Revolving Fund loan, will save an estimated $40 million in interest expenses when compared to conventional bonding sources.
  • July 20, 2015: City creates Facebook event for the construction of the Liberty Utilities Operation Center where people can follow the progress of the project.
    • People can also watch the progress through a live feed webcam.
  • September 29, 2014: The Liberty City Council approved contract with Goodwin Bros. Construction Co. for design and construction of the City of Liberty wastewater treatment facility.
  • April 15, 2014: 3 design-build teams selected to respond to the City's Request for Proposals:
    • Burns and McDonnell/CAS Constructors
    • Goodwin Brothers/CMT
    • HDR/Layne
  • March 7, 2014: Meeting for design and construction industry members , along with related industry partners. The presentation focused on the request for qualifications and provided information on the procurement process and preliminary project schedule.
  • February 28, 2014: City of Liberty issues a Request for Qualifications for Design-Build Procurement (PDF).
  • February 2014: Contracted for technical engineering services with Veenstra & Kimm, to assist in developing performance criteria, establishing metrics, and substantiation/affirmation of design and constructed improvements of the Wastewater Treatment facility project. 
  • November 2013: Contracted with Acquisition Consultant, DesignSense Incorporated, for expertise and assistance in evaluation, selection and contracting for acquiring the Wastewater Treatment Facility and Conveyance Improvements.
  • August 6, 2013: Liberty voters approved the issuance of $95 million in bonds for the construction of a wastewater treatment facility and improvements to the conveyance system by 91%.
  • June 2013: Wastewater Treatment Facility and Conveyance Facility Plan completed
  • 2012: Wastewater Treatment Facility Feasibility Study completed